A pdf of this map can be downloaded below.
Start date: September 2, 2025
Anticipated completion date: August 2027
Estimated cost: $12 million
PURPOSE & DESCRIPTION
The purpose of the Rock Island Arsenal Viaduct reconstruction project is to provide the needed replacement of the current bridge deck, parapets, and lighting as well as spot repairs to the steel support beams. The condition of the existing bridge has deteriorated to the point where an upgrade to those elements is necessary.
The 16th Street Viaduct Bridge intercepts 4th Avenue and 14th Street at street level and passes over existing streets and businesses to its connection with the Arsenal Island Bridge just north of River Drive. The bridge provides direct access for commuters wishing to travel between Arsenal Island and Moline. Weather, salt used in snow removal, vehicle use, and age have combined to result in deterioration of the bridge deck and the need for repairs.
A pdf with more information about the project's purpose and description can be downloaded below.
PROJECT TIMELINE (updated 8/6/25)
7th Avenue in Moline is under construction in 2025.
Phase I - 15th Street to 16th Street
Start date: May 5, 2025
Anticipated completion date: August 30, 2025
The photo at left shows road closures for Phase I of this project.
Phase II - 16th Street to 19th Street
Anticipated start date: September 2, 2025
Intersections at 17th and 18th Streets will be closed during Phase II
Anticipated end date: Fall 2025
Single-lane roundabouts will be installed at 15th St and 18th St
PDF's of this map, preliminary design work for this project, and FAQs about this project are available for download below.